2022· Construction Business and Project Management Conference· pp. 374-383· 0 citations· 19 references
Abstract
Mega construction projects have various scopes executed by more than one contractor. Poor coordination of the scheduling and execution of the contractors can lead to
exorbitant claims. The purpose of this study was to determine cost overrun factors that could lead to construction claims in a multi-contractor set-up for a mega project. The
study employed a quantitative research approach. The study adopted a purposive sampling technique with a sample size of 50 respondents. Data was collected with a
survey questionnaire from professionals involved in the design and execution of projects within the construction industry, based in Gauteng province in South
Africa. The respondents include Construction Project Managers and Quantity Surveyors. Results of the survey were analysed using the relative importance index
statistical method, which resulted in the identification of the cost overruns factors that could lead to construction claims for a multi-contractor construction project. The
findings of the study reveal that cost overrun factors responsible for construction claims include design changes, construction complexity, contracts management, access to site,
and coordination of the work of the contractors, incompetence of the contractor and poor planning. Construction management companies should work together with the employer to develop practices to manage construction activities in order to avoid construction claims.
Most of the construction projects fail to be completed within cost and time. This study aimed to assess the project risk factors that lead to construction cost overruns. The study
employed a quantitative research approach. A purposive sampling technique was used to source data from a sample size of 50 respondents. A su...
M. Tshehla· Construction Business and Pr...· 0 citations
Mega construction projects are often associated with high-cost overruns. Most of these costs are associated with construction claims. The contractors mostly submit these claims against the employer. Contractors can successfully defend their claims. Some of these claims are supposed to be apportioned between the two par...
M. Tshehla· Construction Business and Pr...· 0 citations
Many construction projects have experienced cost underruns with no research to investigate the drivers for the cost underruns. Hence, this study investigated the key
drivers of construction cost changes in the South Africa. A quantitative method research approach was employed in obtaining data for this study. The signi...
A. Windapo, Emmanuel Dele Omopariola, I. Albert et al.· Construction Business and Pr...· 0 citations
Road construction projects in Tanzania continue to experience persistent cost overruns, undermining infrastructure development and broader economic growth. This study employs probit regression analysis to identify the key factors influencing cost escalation in road construction projects. The main objective was to deter...
F. A. Rwechungura· Journal of Sustainable Resea...· 0 citations
The purpose of this study is to evaluate the various challenges encountered by bid
evaluators in Engineering, Procurement and Construction (EPC) contract bid evaluation,
The reason for the outcome of this study is as a result of improper bid management
system in EPC contracts resulting to poor project performance by in...
Ogbevire Dsilvia Ejovi, N. Saka· Construction Business and Pr...· 0 citations
Effective claims management is essential in construction projects, particularly in the oil and gas sector, where disputes
can lead to significant cost and schedule overruns. This study focuses on identifying and preventing claims in oil and
gas piping construction projects—a critical yet underexplored area. A systemati...
Saeed Raeisi, M. Bagherpour· Journal of Construction Engi...· 0 citations
We use cookies to run the site and, with your consent, for analytics and to show ads.
See our Cookie Policy.