Exact SAT and Constraint Programming for Job Shop Scheduling with Time-Varying Peak Power Constraints
The Job Shop Scheduling Problem with Power Requirements (JSPPR) extends the classical job shop scheduling problem by imposing time-varying limits on instantaneous power consumption. Previous studies have used a mixed-integer linear programming formulation and the GRASP x ELS metaheuristic, but no SAT-based exact approa...